Post launch and LEOP status
ATV Albert Einstein is performing nominally! That’s engineer-speak that means, “Everything’s OK…” The update below is an extract from the mission report for 6 June sent by ATV-CC. Note all upcoming activities are subject to change.
GENERAL STATUS
- Successful Ariane 5 mission and ATV LEOP (Launch and Early Orbit Phase) activities
- ATV is nominal, in free flight at 260km
ATV STATUS
- All subsystems nominal
- Increase of temperatures for some components due to high beta angle [or position of the Sun relative to ATV] and no eclipse. No issues. Nominal management and monitoring by ATV-CC.
EXECUTED OPERATIONS
- June 05 : ATV launch at 21:52:11 UTC / separation 22:56:04 UTC, as planned
NEXT OPERATIONS. MAIN ACTIVITIES
- till June 10, freeflight with monitoring and routine activities
- June 10 : Second part of LEOP (SADM [Solar Array Drive Mechanism] cleaning 05:18:17 UTC)
- June 10 : first TPO [Transfer to Phasing Orbit] manoeuvres
- June 11 : CAM [Collision Avoidance Manoeuvre] test 15:30:00
- June 11 : Progress 51P undocking 13:50:00
- June 15 : ATV Docking at 22:33 UTC (tbc)
- June 17 : Initial Ingress
- June 17 or 18 : Final Ingress
- July 10 : Reboost manoeuvre #01 (tbc)
- August 02 : First Gas Transfer (tbc)