The IMMT – the ISS Mission Management Team (IMMT), the coordinating body comprising all ISS partner agencies (ESA, NASA, JAXA, CSA, Roscosmos/RSC-E) – has given the ‘go’ for ATV-4 undocking, set for Monday 28 October. This marks the start of a series of steps that will prep the ESA cargo vessel for departure followed by a controlled destructive re-entry on 2 November. Egress and final hatch closure are set for Friday, 25 October, at 16:00 CEST.
Note as always: All dates/timings below are forecast only and are subject to change as this is a continuing, dynamic mission. Time below indicated in UTC.
GENERAL STATUS
- ATV and ATV-CC nominal
- All cargo delivered and trash loaded
- Successful last reboost
- IMMT GO for undocking
- Green for final EGRESS and ATV preparation before hatch closure and undocking
- ATV STATUS
- Attached dormant mode
- Cabin fan switched Off
ATV-CC STATUS and ATV GROUND SEGMENT
- All ATV-CC systems nominal
- ATV monitoring and routine attached activities
CARGO and FUEL STATUS
- Dry cargo : 2 489kg /100% transferred
- Accepted trash : 1657kg
- Accepted liquid waste : 503 l
- Water : 564kg /100% transferred
- Air (2 tanks) : 66kg /100% transferred
- Oxygen (1 tank): 33.3kg/100% transferred
- Refuelling propellant : 860kg/100% transferred
EXECUTED OPERATIONS
- 19 October : PCE test between ISS-ESOC Ground Station
- 21 October: Last liquid waste transfer
- 22 October: Orbital D1 unberthing (no ATV support)
- 22 October : Close-out imagery
- 23 October : 3rd refuelling vacuuming
- 24 October: Reboost #6 (0,62m/s, used 86kg)
- 24 October : ATV equipment gathering, removal of ATV items to be kept in ISS
NEXT OPERATIONS. MAIN ACTIVITIES
Preparation for undocking/reentry
- 25 October : Hatches closure (ATV at 14:00 UTC)
- 25 October : Crew OBT training before undocking
- 28 October: ATV4 undocking (separation 08:59 UTC)
- 28 October : ATV in freeflight. Phasing TPO manoeuvres
- 31 October : MC manoeuvers
- 01 November : TIV manoeuvers
- 02 November : Reentry
Discussion: no comments