All quiet with ATV in space this week! Air transfer to ISS planned for Friday.
Note as always: All dates/timings below are forecast only and are subject to change as this is a continuing, dynamic mission. Time below indicated in UTC.
GENERAL STATUS
- ATV Operations nominal
- Cabin fan switched Off
ATV STATUS
- Attached dormant mode,
ATV-CC STATUS and ATV GROUND SEGMENT
- All ATV-CC systems nominal
- ATV monitoring and routine attached activities
CARGO and FUEL STATUS
- Dry cargo : 2 489kg /100% transferred
- Accepted trash : 1238kg
- Accepted liquid waste : 328 l
- Water : 564 Kg /100% transferred
- Air (2 tanks) : 13.8kg available (transferred 52.5kg/79%)
- Oxygen (1 tank): 33.3kg/100% transferred
- Propellant : used 1246kg, available for ISS supports : 2236kg
- Refuelling propellant : initial 860kg, 100% transferred
EXECUTED OPERATIONS
- 15 September: Reboost 0.50m/s
- 16 September: Thruster T402 firing test
- 19 September: Thruster T402 re-integration
- 19 September: Liquid Waste Transfer
- 19 September: Air Mix Transfer
NEXT OPERATIONS. MAIN ACTIVITIES
- 22 September: Orbital D1 berthing (Delayed)
- 25 September: ISS attitude change
- 26 September: 36 docking (bu 27/28). ISS attitude change
- 27 September: Air Mix Transfer
- 01 October: Liquid Waste Transfer (tbc)
- 02 October: Reboost (placeholder. 2.34m/s, bu 04Oct)
- 04 October: Liquid Waste Transfer (tbc)
- 04 October: Air Mix Transfer (tbc)
- 22 October: Orbital D1 unberthing
Discussion: no comments