The ATV hatch was reopened on 23 August after being shut for a week while Albert Einstein was configured for the Russian EVAs on 16 and 22 August.
Planned events in the last week of August: Water transfer from ATV’s tank 3 (84 litres, leaving Tank 3 empty), O2 transfer, Air transfer and, on 31 August, Reboost No. 2, set for a 0.3 m/sec speed boost.
Note as always: All dates/timings below are forecast only and are subject to change as this is a continuing, dynamic mission. Time below indicated in UTC.
GENERAL STATUS
- ATV hatch closed from 15 August to 23 August
- ATV hatch re-open to-day
- ATV nominal
ATV STATUS
- Attached dormant mode
ATV-CC STATUS and ATV GROUND SEGMENT
- All ATV-CC systems nominal
- ATV monitoring and routine attached activities
CARGO and FUEL STATUS (no change)
- Dry cargo : initial 2 489kg, 100% transferred
- Accepted trash : 1224kg
- Accepted liquid waste : 175 l in tank 1
- Water : 151kg available (transferred 414Kg/73% )
- Air (2 tanks) : 48.4kg available (transferred 17.9kg/27%)
- Oxygen (1 tank): 23.4kg available (transferred 9.9kg/30%)
- Propellant : used 1108kg, available for ISS supports : 2 332kg
- Refuelling propellant : initial 860kg, 100% transferred
EXECUTED OPERATIONS
- 19-23 August : ATV-CC and Ground Segment maintenance activities
NEXT OPERATIONS. MAIN ACTIVITIES
- 23 August : ATV hatch opening (after EVA performed from 16 to 22 August. fan reactivated during the opening activities)
- 23 August: Liquid waste transfer to tank 1 (-> tank 1 full)
- 23 August: Water transfer from tank 3 (66 litres)
- 26 August: Water transfer from tank 3 (84 litres -> tank 3 empty)
- 26 August: Water tank 3 bladder integrity checked
- 29 August : O2 transfer
- 30 August : Air transfer
- 31 August : Reboost #2 (bu 2 Sept) 0.3m/s
- 03 September: ATV-05 SVT-1 (bu 04 Sept)
- 05 September: O2 final transfer
- 06 September: Air transfer
- 11 September: 34S undocking
- 13 September: Reboost #3 (bu 14Sept) 0.4m/s
- 22 September: Orbital D1 berthing
- 26 September: 36S docking
- 02 October: Reboost #4 (placeholder)
- 22 October: Orbital D1 unberthing
- 25 October: Reboost #5 (placeholder)