17 Jan – JORR – Joint Operations Readiness Review – complete
1 Feb – FAR – Final Acceptance Review – complete
3 Feb – ORR – Operations Readiness Review – complete
6 Feb – ATV-3 ready to move to BAF at Kourou (Final Assembly Building)
16 Feb – SORR – Stage Operations Readiness Review
1 Mar – LRR – Launch Readiness Review
2 Mar – RAL – Revue Aptitude Lancement (for Ariane 5, our launcher)
9 Mar – lift-off (scheduled) – at 11:00 CET